The Create WBS process identifies the deliverables at the __________ level in the Work Breakdown Structure (WBS).
A. Lowest
B. Any
C. Tenth
D. Highest
Answer: A
Which of the following statements most accurately describes a project scenario?
A. Changes in project scope during the initial phases of the project are very expensive.
B. The influence of the stakeholders is the same all through the project.
C. Staffing peaks up during the execution phase of a project.
D. The next phase of a project should never start until the deliverables for the previous phase have been completely reviewed and approved.
Answer: C