Which of the following is not an organizational process asset that is used during the Plan Human Resource Management process?

A. Template for organizational charts
B. Template for position descriptions
C. Standardized role descriptions
D. Standardized stakeholder list

Answer: D
 

Perform Integrated Change Control includes several configuration management activities. Which of the following is not part of Perform Integrated Change Control?

A. Change request
B. Configuration Verification
C. Configuration Status Accounting
D. Configuration Identification

Answer: A