Question No: 3
A benefit-cost ratio of 3.22 indicates a:A. Profit of s3.22 per unit produced.
B. Profit of s3.22 for each dollar expended.
C. Resources assigned to other tasks on the critical path.
D. Payback of s3.22 for each dollar expended.
Answer: D
Question No: 4
Certain resources have been added to tasks on the critical path so as to reduce the project duration. As a result the plan should then be reviewed for the:A. Possible lag time on other paths.
B. Resource assigned to other tasks on the critical path.
C. The most time consuming task remaining in the plan.
D. Emergence of a new critical path.