Question NO: 5
During a software project Earned Value Analysis is performed and gives the following results:EV: 523,000;
PV: 623,000;
AC: 643,000.
Which results are correct?
A. CV: +120,000; SV: +100,000.
B. CV: +100,000; SV: +120,000.
C. CV: -100,000; SV: -120,000
D. CV: -120,000; SV: -100,000.
Answer: D
Question NO: 6
Which of the following is not normally an element of the Project Charter?
A. The formal authorization to apply organizational resources to project activities.
B. Work package descriptions.
C. The business need that the project was undertaken to address.
D. The product description or a reference to this document