Thursday, 8 October 2015

Pass4sure PMP Question Answer

Which document defines how a project is executed, monitored and controlled, and closed?

 

A. Strategic plan
B. Project charter
C. Project management plan
D. Service level agreement


Answer: C

 

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

 

A. Risk and uncertainty increase; the cost of changes increases.
B. Risk and uncertainty increase; the cost of changes decreases,
C. Risk and uncertainty decrease; the cost of changes increases.
D. Risk and uncertainty decrease; the cost of changes decreases.


Answer: C