A project manager in a predominantly hierarchical organization has been assigned a major project with aggressive timelines. The BEST approach for developing an initial project charter in this environment is to:
A. Create a project charter using brainstorming sessions with potential team members and stakeholders.
B. Create and present a draft project charter to potential team members and stakeholders to solicit their input.
C. Create a project charter jointly with management for distribution to potential team members and stakeholders.
D. Create a project charter with the functional managers and present it to the sponsor for signature.
Answer: C
All of the following are correct statements about a project manager EXCEPT:
A. He or she is assigned after the project charter is created.
B. He or she may initiate changes to the project.
C. He or she manages changes and factors that create change.
D. He or she is held accountable for project success or failure.
Answer: A