Pass4sure PMP Question Answer

What is one of the KEY objectives during contract negotiations?

A. Obtain a fair and reasonable price.
B. Negotiate a price under the seller's estimate.
C. Ensure that all project risks are thoroughly delineated.
D. Ensure that an effective communications management plan is established.

Answer: A

You are a new project manager who has never managed a project before. You have been asked to plan a new project. It would be BEST in this situation to rely on _______ during planning to improve your chance of success.

A. Your intuition and training
B. Stakeholder analysis
C. Historical information
D. Configuration management

Answer: C