Friday, 6 May 2016

Pass4sure PMP Question Answer

Daniel is managing the development of an ecommerce website for his organization. Daniel enjoys coercive powers and has assigned Julie, a project team member, to facilitate the team meetings. During any team meeting, Julie must?

A. Influence team members to support the project manager's decisions
B. Support the team members to challenge the project manager's decisions
C. Negotiate with team members to achieve the project objectives
D. Remain neutral and facilitate the meetings

Answer: D

No comments:

Post a Comment