The most detailed level of the WBS is called the _______________ .
A. WBS element
B. Work package
C. Project scope
D. Deliverable
Answer: B
Which of the following is a hierarchical representation of project risks?
A. Risk Register
B. Risk Mitigation
C. Risk categories
D. Risk Breakdown Structure
Answer: D