Monday, 6 November 2017

PMI PMP Question Answer

The most detailed level of the WBS is called the _______________ .

A. WBS element
B. Work package
C. Project scope
D. Deliverable

Answer: B


Which of the following is a hierarchical representation of project risks?

A. Risk Register
B. Risk Mitigation
C. Risk categories
D. Risk Breakdown Structure

Answer: D

No comments:

Post a Comment