During the Plan Procurement Management phase, the make-or-____analysis must be completed. This technique prompts the project team to determine the source of their item.
A. lease
B. buy
C. find
D. ignore
Answer: B
Which of these precedence relationships is least commonly used in Precedence Diagramming Method?
A. Start to Start
B. Finish to Finish
C. Finish to Start
D. Start to Finish
Answer: D