Sunday 23 September 2018

PMI PMP Question Answer

During the Plan Procurement Management phase, the make-or-____analysis must be completed. This technique prompts the project team to determine the source of their item.

A. lease
B. buy
C. find
D. ignore

Answer: B


Which of these precedence relationships is least commonly used in Precedence Diagramming Method?

A. Start to Start
B. Finish to Finish
C.
Finish to Start
D. Start to Finish

Answer: D

No comments:

Post a Comment