Which process of integrative project management documents the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans into a project management plan?
A. Direct and Manage Project Work
B. Monitor and Control Project Work
C. Develop Project Charter
D. Develop Project Management Plan
Answer: D
Mary is currently focusing on controlling the key stakeholder engagement on her project. The project management plan is an essential input to this process. Which of the following components of the project management plan is least likely to be utilized during this process?
A. Stakeholder communication needs and expectations
B. Project management processes selected for the project
C. Change management process
D. Human resource requirements
Answer: B
Tuesday, 28 January 2020
Sunday, 29 September 2019
PMI PMP Question Answer
If you are writing a proposal for additional funding, which communication style should you choose?
A. formal and horizontal
B. formal and vertical
C. informal and vertical
D. informal and horizontal
Answer: B
If you want a group of experts to identify project risks, but also want unbiased data, what is an appropriate technique to use?
A. Interviewing
B. Delphi technique
C. Assumption analysis
D. Brainstorming
Answer: B
A. formal and horizontal
B. formal and vertical
C. informal and vertical
D. informal and horizontal
Answer: B
If you want a group of experts to identify project risks, but also want unbiased data, what is an appropriate technique to use?
A. Interviewing
B. Delphi technique
C. Assumption analysis
D. Brainstorming
Answer: B
Monday, 14 January 2019
PMI PMP Question Answer
A RACI chart is an example of a _________________.
A. Network
B. Flowchart
C. Responsibility assignment matrix
D. Hierarchical-type organization chart
Answer: C
Your company has temporarily assigned you to serve as a project manager at a company location outside your home country. While meeting with a vendor your first day on the job, you are presented with a gift. The corporate policy at the headquarters in your home country prohibits employees from accepting these types of gifts. However, as you are new to this location, you believe- but are not sure-that the local policy, as well as local custom may differ. How should you respond?
A. Provide a gift of similar value to the vendor at your next meeting.
B. Accept the gift but do not tell anyone.
C. Respectfully tell the vendor you are not sure of corporate policy, and will need to ask your management before you can accept gifts of any size.
D. Accept the gift this time, but ask your manager about the local policy afterwards.
Answer: C
A. Network
B. Flowchart
C. Responsibility assignment matrix
D. Hierarchical-type organization chart
Answer: C
Your company has temporarily assigned you to serve as a project manager at a company location outside your home country. While meeting with a vendor your first day on the job, you are presented with a gift. The corporate policy at the headquarters in your home country prohibits employees from accepting these types of gifts. However, as you are new to this location, you believe- but are not sure-that the local policy, as well as local custom may differ. How should you respond?
A. Provide a gift of similar value to the vendor at your next meeting.
B. Accept the gift but do not tell anyone.
C. Respectfully tell the vendor you are not sure of corporate policy, and will need to ask your management before you can accept gifts of any size.
D. Accept the gift this time, but ask your manager about the local policy afterwards.
Answer: C
Sunday, 23 September 2018
PMI PMP Question Answer
During the Plan Procurement Management phase, the make-or-____analysis must be completed. This technique prompts the project team to determine the source of their item.
A. lease
B. buy
C. find
D. ignore
Answer: B
Which of these precedence relationships is least commonly used in Precedence Diagramming Method?
A. Start to Start
B. Finish to Finish
C. Finish to Start
D. Start to Finish
Answer: D
A. lease
B. buy
C. find
D. ignore
Answer: B
Which of these precedence relationships is least commonly used in Precedence Diagramming Method?
A. Start to Start
B. Finish to Finish
C. Finish to Start
D. Start to Finish
Answer: D
Wednesday, 21 February 2018
The Project Management Professional Certification Training Bundle Is Up For A 98% Discount Offer – Limited Time Deal
Project management is no doubt a great career but it requires a lot of investment in the form of resources, time, hard work etc. So, how do we go about all these problems? Well, you don’t have to give it a lot of thought. Wccftech is here with a solution. We are offering an amazing discount on The Project Management Professional Certification Training Bundle. With this bundle you will get lifetime access to the course content.
Project Management Professional Certification Training Bundle features
The bundle includes 10 extremely comprehensive courses. This bundle is your key to excelling in the project management field. So are you willing to invest? Or do you still need more convincing? Here are highlights of what each course has to offer:
Project Management Professional (PMP) – Increase Your Employability & Salary with This Industry-Recognized Certification
Certified Associate In Project Management (PMI-CAPM) – Get a Comprehensive Introduction to Project Management & Give Your Career a Boost
Risk Management Professional (PMI-RMP) – Take the Risks Out of Project Management by Becoming a Certified Risk Manager
CompTIA Project+ PK0-003 – Get Familiar with the Project Lifecycle & Learn One of the Most Important Positions in IT
Six Sigma Green Belt – This 20-Hour Course Will Get You Up to Speed on All Things Six Sigma
Six Sigma Black Belt – Elevate Your Career Prospects by Mastering Six Sigma
PRINCE2 Foundation – Take the First Step Toward PRINCE2® Certification
PRINCE2 Practitioner – Delve Into One of the Most Rapidly Growing Project Management Methodologies
Information Technology Infrastructure Library (ITIL) Service Operation – Learn the Best Practices for Service Operation in the IT Industry
The bundle has been designed by iCollege. The company is known as a leading provider of e-learning courses, learning technologies and development services. This platform is basically a collaborative venture of XpertSkills and XpertEase Software. This combination of companies has been very ideal for business and hence iCollege has been able to provide sophisticated, innovative, flexible and cost-effective learning solutions.
Wednesday, 20 December 2017
PMI PMP Question Answer
Which of the following is a tool or technique used in the Monitor and Control Project Work process?
A. Expert judgment
B. Rejected change requests
C. Earned value technique
D. Change control tools
Answer: A
A large network hardware upgrade project was scheduled to take place over a weekend. During the course of the implementation, several previously unidentified dependencies for additional materials were discovered. The project manager gave approval for the tech staff doing the implementation procure with corporate credit cards several hundred dollars worth of additional equipment required to complete the implementation. However these additional expenses caused the project to exceed its budget. How should the project manager handle this?
A. Ask the IT Director to cover those expenses from his budget.
B. Advise the staff to submit expense reports for the purchases. Because the cost is relatively small, it can be categorized as miscellaneous purchases that are not associated with the project.
C. Notify the project stakeholders immediately of the additional expenses incurred and follow project and or company procedures for budget variances.
D. Do nothing- that's what reserves are for.
Answer: C
A. Expert judgment
B. Rejected change requests
C. Earned value technique
D. Change control tools
Answer: A
A large network hardware upgrade project was scheduled to take place over a weekend. During the course of the implementation, several previously unidentified dependencies for additional materials were discovered. The project manager gave approval for the tech staff doing the implementation procure with corporate credit cards several hundred dollars worth of additional equipment required to complete the implementation. However these additional expenses caused the project to exceed its budget. How should the project manager handle this?
A. Ask the IT Director to cover those expenses from his budget.
B. Advise the staff to submit expense reports for the purchases. Because the cost is relatively small, it can be categorized as miscellaneous purchases that are not associated with the project.
C. Notify the project stakeholders immediately of the additional expenses incurred and follow project and or company procedures for budget variances.
D. Do nothing- that's what reserves are for.
Answer: C
Monday, 6 November 2017
PMI PMP Question Answer
The most detailed level of the WBS is called the _______________ .
A. WBS element
B. Work package
C. Project scope
D. Deliverable
Answer: B
Which of the following is a hierarchical representation of project risks?
A. Risk Register
B. Risk Mitigation
C. Risk categories
D. Risk Breakdown Structure
Answer: D
A. WBS element
B. Work package
C. Project scope
D. Deliverable
Answer: B
Which of the following is a hierarchical representation of project risks?
A. Risk Register
B. Risk Mitigation
C. Risk categories
D. Risk Breakdown Structure
Answer: D
Subscribe to:
Posts (Atom)