After brainstorming potential project risks, what is the recommended method for prioritizing these risks and their mitigation plans?
A. RACI chart
B. Control chart
C. Fishbone Diagram
D. Probability and impact matrix
Answer: D
If you are influencing factors that create changes to the cost of the project, which process are you using?
A. Negotiate Costs
B. Estimate Costs
C. Control Costs
D. Determine Budget
Answer: C